|
Sunrise Powerlink alternatives bisect Back Country
By Christy
Scott
The Alpine Sun
SAN DIEGO — In a report issued in March, the
California Public Utilities Commission decided to keep three southern
routes for the 500-kilovolt Sunrise Powerlink power line as possible
alternatives to the preferred route through Anza-Borrego State Park.
The three southern alternative routes however, would
cut right through the communities of Jacumba, Boulevard, Campo, Pine
Valley, Descanso and Alpine, as well as through large parts of the
Cleveland National Forest.
The report was issued after months of review, during
which comments from local agencies and residents were solicited at
various community meetings. But officials for the Cleveland National
Forest were late gathering their comments and didn’t submit them in
time.
“They didn't get any input from us before reaching
their conclusions,” one forest official said. Project officials say
that more input will be gathered during the environmental impact
report period, and the forest officials will have plenty of time to
weigh-in.
Forest officials oppose the southern options. One that
would parallel Interstate 8 for many miles would not be consistent
with a national forest land-management plan, and there are fire
suppression and emergency response concerns, they argue in a letter to
the commission. High-voltage wires could interfere with air tankers
dumping fire retardant on flames in an area where many rural
communities are, the letter says.
SDG&E's preferred route for the 150-mile, $1.3 billion
transmission line would not pass through the forest at all. It starts
in the Imperial Valley, where wind and solar energy are expected to be
developed; cuts through the middle of Anza-Borrego Desert State Park;
and ends at a substation near Del Mar.
The powerlink proposal has met stiff opposition from
residents in the line’s path and from environmentalists, who say it is
unnecessary. SDG&E contends the line is needed to ensure regional
electric reliability and allow for the import of power generated from
renewable energy sources.
After the initial project was proposed last year, the
PUC ordered SDG&E to come up with several alternative routes that
would avoid Anza-Borrego.
“The PUC has told us that we have to look for another
route,” said SDG&E representative Nick Pince. “They want us to find a
route that doesn’t go through the Anza-Borrego State Park.”
SDG&E has said the three alternative southern routes it
reviewed are undesirable because they are close to a power line that
has been knocked out of service by fire 23 times in the past decade.
Having a second power line so close increases the risk that both could
go out of service in a disaster, negating the main reasoning for the
Sunrise routes.
“I want to stress that SDG&E has already rejected these
routes in preliminary studies because they are too costly, and don’t
meet the demand that we want, Pince said.
Many critics have argued that the line isn’t needed in
San Diego, for renewable energy or reliability.
“It’s a false choice,” said Sierra Club representative
Kelly Fuller, of Alpine, regarding the alternative routes. “Anywhere
they’re going to do this, it’s just not needed.”
“We don’t want to make this a fight between the North
County and the East County about where to put this transmission line,”
Fuller said. “All this looking at alternative routes is taking away
from the main focus, which should be exploring alternatives that don’t
require a power line.”
According to Jim Avery, vice president of electric for
SDG&E, the project is not only for future needs, it is crucial for
complying with a new state law that says all major utilities must
secure 20 percent of their power from clean fuel sources, which aren't
fossil, by 2010.
With the recent approval by the CPUC on March 20, SDG&E
took a step in that direction with four new renewable energy
contracts.
The contracts total about 140 megawatts of solar,
biomass and geothermal energy. While SDG&E finalized the contracts
last year with companies in San Diego and Imperial counties, the CPUC
approval gives the official green light for the utility to move ahead
with these projects.
Esmeralda San Felipe Geothermal LLC will provide 20 MW
of geothermal power by December 2010 using heat from beneath the
earth's surface to generate electricity and provide heat. Bethel
Solar's two contracts will deliver a total of 100 MW of electricity in
two phases in June and December 2008 from solar-power technology,
which uses solar-cell troughs that follow the sun's movement during
the day to convert energy from the sun into electricity at two sites
in Imperial Valley.
If completed as envisioned by the utility, the electric
transmission line would stretch 150 miles from Imperial County across
northern San Diego County and cost about $1.3 billion to construct.
The towers along the route would be gigantic metal structures,
measuring 125 feet high and more than 100 feet wide at their base.
Proposed for completion in 2010, the project would
deliver 1,000 megawatts to the region, or roughly one-fourth of what
it currently uses on the hottest days. A megawatt is the standard
measuring unit of electricity and is generally enough to keep the
lights on in 750 to 1,000 homes. But obviously much more energy is
needed during the summer.
The draft EIR/EIS is expected to be completed in July
of this year. The agencies expect to lean heavily on that report as
they decide by January 2008 whether to issue permits for the project.
Planning groups in Boulevard, Pine Valley and Campo
have voted to deny the Sunrise project in its entirety, including all
alternative routes. Groups in Descanso and Jacumba also expressed
discontent after presentations by SDG&E representatives regarding the
powerlink.
E-mail
the Editor
|