|
Powerlink decision postponed at least five months
By Christy Scott
The Alpine Sun
SAN DIEGO — A month-long set of hearings
discussing the proposed Sunrise Powerlink has been postponed, after
an admission by San Diego Gas & Electric that it made significant
errors in estimating the benefits of its powerlink project.
Steven Weissman, administrative law judge for the
Public Utilities Commission, who has been overseeing the hearings,
made the call two weeks ago, to postpone all hearings until July 30.
After a telephone conference in late July, Weissman went one step
further, indefinitely postponing the remainder of the hearings.
The hearings, which began at the beginning of July,
have featured expert testimony in various categories regarding the
powerlink project. They were scheduled to end this week.
Last month, SDG&E’s grid planning manager Jan Strack
testified that he became aware of several significant errors in
making the case for the Sunrise Powerlink to the PUC.
According to SDG&E, mistakes involved misplaced decimal
points, as well as other errors regarding the availability of
coal-fired power plants in 2020.
Strack said that the errors made him uncomfortable
about the case SDG&E has presented, and called for the
“top-to-bottom” review.
SDG&E representatives said that the utility would
correct the errors by the end of last week week, and review the
entire economic case this week.
When first proposed, in 2005, SDG&E estimated an annual
energy cost savings of $447 million; that estimate was later lowered
to $220 million. The report released by SDG&E, last Friday, drops
the savings again, estimating $129 million in annual cost reductions
to consumers.
Michael Niggli, chief operating officer of SDG&E, said
that the new estimate doesn’t change the overall benefit of the
Sunrise project to the region.
“The primary reasons we are looking at Sunrise are
reliability and renewables,” Niggli said. “It has never been the
economic benefits, even though it has twice the benefit of
alternatives.”
The newest numbers also reduce the benefits of all the
project alternative routes.
SDG&E’s preferred Sunrise Powerlink route stretches 150
miles from Imperial County across northern San Diego County, through
Anza Borrego State Park, and would cost about $1.3 billion to
construct. The towers along the route would be gigantic metal
structures, measuring 125 feet high and more than 100 feet wide at
their base.
Other alternative routes that have been identified by
the CPUC could plant conduit towers along a path that would skirt
Cleveland National Forest land; but travel right through Boulevard,
just north of Campo, Potrero, and then north through Descanso and
Alpine, where it would be underground.
The concession last week, of SDG&E errors, also
prompted the Division of Ratepayer Advocates, a unit of the
California Public Utilities Commission, to call for a dismissal of
the case, which could derail the project.
“This eviscerates their case,” said Joe Como, an
attorney with the Division of Ratepayer Advocates. “You might get a
witness saying there are small areas requiring change here and
there… This time the witness says this upsets the whole apple cart.”
Weissman deferred ruling on the dismissal motion last
week, saying that the question is still on the table.
In another project setback, the draft environmental impact report (EIR)
for the project, due to be released this week, will now likely not
be completed until early next year.
California PUC Commissioner Dian Grueneich, who made
the announcement, blamed SDG&E for the delay. She said SDG&E held
back key information on three issues about Sunrise Powerlink from
state and federal officials until as late as a few weeks ago.
This gave California PUC and U.S. Bureau of Land
Management staff too little time to study the environmental impact
of the changes, Grueneich wrote in her report.
SDG&E "continues to delay in responding to
environmental staff questions on several key issues," such as rare
plant and animal species that would be affected by their proposals,
Grueneich wrote.
"By extending the schedule for the release of the draft
EIR, I am necessarily extending the timing of a final Commission
decision," Grueneich wrote.
"In all likelihood, this means that the proposed
Sunrise Powerlink, if approved, could not be in service by 2010."
She does not expect the draft of the environmental review documents
for the Powerlink to be released until summer 2008.
The three issues that, Grueneich said, require more
study before an EIR can be drafted are:
SDG&E's identifying possible expansion on its preferred route for
the Sunrise Powerlink.
Plans for a power substation to connect to wind farm generators.
The claim by SDG&E that it would not meet stringent state
requirements to deliver renewable-generated power such as wind and
solar without Sunrise Powerlink.
SDG&E is asking the PUC to reconsider the delay, which
would set the project back by at least five months.
A report by SDG&E released last week says that the
utility wants the delay reduced to no more than one month, arguing
that to wait any longer would keep the San Diego region from
complying with a state mandate to use more renewable power by 2010.
E-mail
the Editor
|