|
Live Oak operator blames
wildfires for not fixing system
By Neal Putnam
The Alpine Sun
SAN DIEGO — Nazar Najor, the operator of a
Live Oak Springs water system who pleaded guilty to giving a false
report about his water safety, told a judge on Friday he hasn't been
able to dig a new well as required because all the qualified workers
to help him do that are busy rebuilding homes lost in the October
2007 wildfires.
Najor, 63, of Boulevard, won a delay in his sentencing
until April 11 by San Diego Superior Court Judge Robert O'Neill.
Najor's attorney, Manuel Rios, gave the judge a 1 1/2 page summary
of all the actions Najor has completed since he pleaded guilty on
June 26.
Najor has sealed up a contaminated water line in Live
Oak Springs that brought him to court in the first place. He
submitted a false lab report to the county Department of
Environmental Health that stated his water system was free from
bacteria.
In fact, a lab report showed the presence of total
coliform bacteria in the water. Operators of small water systems are
required to submit periodic reports on water quality to officials.
O'Neill had ordered Najor to close the contaminated
well and also come up with an alternative water source.
Deputy District Attorney Karen Doty opposed the sentencing delay,
but the judge said he wanted to give him more time to complete the
work.
Najor has completed the permit process to install a
well. County officials inspected what he has done so far, and
granted the permit on Nov. 27, according to Najor's summary of
actions. Najor wrote on Nov. 7 he faxed a county worker a request to
perform the required inspection.
“I hired a commercial well driller on Nov. 3. However,
he could not start my job because of other emergencies that came
first because of the wildfires," Najor wrote. "All of the other
commercial well drillers could not start the job until January of
2008."
The well driller did start the job and he "installed
the 50-foot casing and is waiting for the county inspector...to
approve the casing, and then he can complete the job within 10
days."
However, Najor says, in early December, "the county has
informed me that the test needed for a commercial well will take
eight weeks." He wrote the county agency will require 92 tests to be
conducted before the project is complete. "Labs take a minimum of 60
days to complete such tests," Najor added.
In June, Najor completed its name change application,
and his water line is now called the Live Oak Springs Water Company.
He wrote that he could not get loans from banks to do the work.
"Valuable time was wasted" while waiting for the loans
to be approved. In early Nov. he wrote "I was forced to turn to
family members for emergency financing for the water well project."
Najor installed a new fire hydrant to the system, which
proved valuable to firefighters when two fires in Live Oak Springs
occurred before the Oct. wildfires. He says local firefighters used
the new hydrant repeatedly to refill their trucks up to 40,000
gallons of water.
Although the Oct. wildfires did not hit Live Oak
Springs, Najor wrote that evacuees and Red Cross workers were housed
in the area through Nov. 5. He provided them with water.
Due to the wildfires, employees from San Diego Gas &
Electric were unable to provide electricity for the project, Najor
stated. Najor said he would get a 3-phase generator until SDG&E can
complete their work on the well.
Najor remains free on his own recognizance. He is
likely to be placed on probation, but could be fined $25,000, and
may not have to do any time in jail.
E-mail
the Editor
|