|
Powerlink project environmental report released
Draft report points to southern
route as best environmental choice
By Christy Scott
The Alpine Sun
The Sunrise Powerlink project has
reached a new milestone with the release of the Draft
Environmental Impact Report, last Thursday, Jan. 3. The
California Public Utilities Commission and U.S. Bureau of Land
Management report points to various southern alternatives as the
best option for the 500-kilovolt transmission line.
The draft EIR analyzed the proposed San Diego Gas &
Electric route, north through the Anza Borrego state park, as
well as 27 alternatives to the proposed project. The EIR looks
only at the environmental impacts of each alternative.
After looking at all of the potential routes, the
report suggests that one alternative, the Interstate 8
Alternative, with Modified Route D Alternative, is
“environmentally superior” to all the others. The alternative is
also 40 miles shorter than the original SDG&E proposal.
The original route, and SDG&E’s preferred choice would
run through Anza Borrego Desert State Park. State park officials
and environmentalists objected, and many questioned the need for
the line. The 150-mile, $1.3 billion powerline would start in
the Imperial Valley, where wind and solar energy are expected to
be developed; cut through the middle of Anza Borrego; and end at
a substation near Del Mar.
The conduit towers would be giant steel structures
about 125-feet tall, measuring about 100-feet at their base,
cutting a line through the rural Back Country. Landscape
management would be required around each tower to maintain fire
safety.
SDG&E’s proposal would impact the environment in 50
ways that can’t be mitigated, the study says.
|
Sunrise Powerlink Preferred
Choice
and Preferred Alternative
MAP |
|
Sunrise Powerlink preferred alternative route
Interstate 8 with Modified D
Detail from East to West —
MAP 1,
MAP 2,
MAP 3,
MAP 4 |
The preferred alternative would travel overhead from an Imperial
Valley substation west and south along Interstate 8 through the
communities of Jacumba and Boulevard. Through the Campo area the
powerline would follow the Modified Route D option, cutting
south to skirt the southern end of the Cleveland National Forest
and the Hauser Wilderness area.
West of Barrett Lake the route would cut north through
areas of Descanso and Japatul to I-8 adjacent Viejas Casino. At
the West Willows Road exit the line would underground along
Alpine Boulevard to Peutz Valley. At that point it would again
be overhead, cutting north and west through Lakeside.
This preferred route stretches a total of 110 miles,
104 miles overhead; and 6 miles underground. According to the
report, it meets all major project objectives for reliability
and reduced fire risk, and allows for future transmission system
expansion. It also has only 32 unmitigable environmental
impacts, and crosses 16 miles of national forest land, but
within areas that have acceptable land use.
This route would collocate the Sunrise Powerlink lines
with the already existing Southwest Powerlink, which weaves a
route along the border. Opponents of this route, and SDG&E have
both stated that this collocation is not preferred due to
incidents of fire that have knocked out the line 23 times in the
past decade, including most recently during the October Harris
Fire.
SDG&E officials insist that the new powerline is needed
to ensure energy reliability in San Diego County however,
project opponents say the area’s power needs can be met through
other, local, smaller projects. The EIR also points to a range
of non-transmission alternatives to the line, the least
environmentally harmful alternatives, building power plants and
renewable sources in San Diego County, the report says.
The top alternative calls for building one new power
plant that would meet every-day electricity needs: Either a
replacement for the aging plants in Chula Vista or Carlsbad or a
new one at Marine Corps Air Station Miramar. Four smaller power
plants to meet peak demand would also be needed, the report
says, as would an almost equal amount of renewable energy
sources such as wind and solar.
The public has 90 days to review the draft report and
provide comments to the CPUC and BLM. There will be eight public
workshops between Jan. 28 and Feb. 1 to be held in Alpine,
Borrego Springs, El Centro, Pine Valley, Ramona, San Diego,
Temecula, and Warner Springs. Residents will also have a chance
to legally go on record with their comments at Administrative
Law Judge Public Participation Hearings.
Sunrise Powerlink EIR Workshops will be held locally at
the Alpine Community Center, 1830 Alpine Blvd., on Monday, Jan,
28 at 7 p.m., and two at Mountain Empire High School, 3305
Buckman Springs Road, Pine Valley, on Thursday, Jan. 31 at 3:30
and 7 p.m.
An Administrative Law Judge Public Participation
Hearing will be held at MEHS on Monday, Feb. 25, at 6:30 p.m.
This will be an opportunity for residents to go on legal record
with their comments.
The BLM will select a preferred alternative following analysis
of public comments on the draft EIR and further internal review,
compiling the Final project EIR. A decision on the approval or
denial of the Sunrise Powerlink is expected to be made later
this year.
To view the powerlink draft EIR check online at
HERE, or check at your local library. Back Country
planning groups are looking for volunteers to help review the
EIR and become better prepared for the workshops. Please contact
Denise Morse at 889-9033 if you would like to volunteer.
E-mail
the Editor
|