Published weekly

April 30, 2009

Page 1   This week's print edition   Sun Dial briefs Advertising in The Alpine Sun Staff

Planning Group to weigh in
on high school site selection  


By Christy Scott

The Alpine Sun

     ALPINE — At a meeting held last Thursday, April 23, members of the Alpine Planning Group were briefed about the potential sites for the Grossmont Union School District’s Alpine High School. The informational presentation was in advance of a request by GUHSD staff that the APG vote on a preferred site at its regular May meeting.
     GUHSD School Construction & Building Services Executive Director, Bob Kiesling, and 12th High School Facilities Planner Dena Johnson presented the four potential sites that have been identified. Option B — Wright’s Field, is located on the north side of South Grade Road, east of Tavern Road; Option G — Chocolate Summit, consists of two possible spots on the northeast end of Chocolate Summit Drive; and Option J — the Lazy-A Ranch is located on south side of Alpine Boulevard, east of South Grade Road.
     According to the project Environmental Impact Report, which was released at the beginning of the year, option J, the Lazy-A Ranch is the environmentally superior site for the new school.
     “The EIR deals only with the environmental impacts of the project on these sites,” said Kiesling. “And the environmentally superior choice is not the end-all for this decision. The Grossmont board is going to have to look at many different factors.” These factors include displacement of residents currently at the site and overall costs, among others.

Sizing up the sites
Option B — Wright’s Field
     Size: 75 acres – gross, 49.9 acres – net (useable space), on vacant land. There are no dwellings or residents on the site. Unmitigatable environmental impacts include the change in visual character and increased noise, as well as a loss of MSCP native grassland.
     The district looks to save $138,000 with this site, due to the elimination of three bus routes. The total approximate cost for Option B is $12 to $13 million.

Option G-1 — Chocolate Summit
     Size: 72 acres – gross, 61.2 acres – net, on residential and agricultural land (former poultry farm). There are 10 dwellings and about 30 residents who would have to be displaced on this site. Unmitigatable environmental impacts include the change in visual character, increased noise and increased traffic.
     The total approximate cost for Option G-1 is $31 to $34 million.

Option G-2 — Chocolate Summit
     Size: 78 acres – gross, 57.3 acres – net, on residential and agricultural land (former poultry farm). There are two dwellings on this site, with four residents living in the house on the chicken ranch, and four more living in trailers on the site. Unmitigatable environmental impacts include the change in visual character, increased noise and increased traffic.
     The total approximate cost for Option G-2 is $23 to $26 million.

Option J — Lazy-A Ranch
     Size: 92 acres – gross, 47.8 acres – net, on residential, agricultural (horse boarding) and vacant land. There are six dwellings on this site, which house about 17 people. Unmitigatable environmental impacts include the change in visual character and increased noise.
     The district looks to save $115,000 with this site, due to the elimination of two bus routes. The total approximate cost for Option J is $11 to $12 million.

GUHSD 12th High School Schedule
Draft EIR 45-Day Public Review — Complete
Prepare Responses — mid-April
Draft Findings — April 30
Issue Final EIR to agencies — May 4
Prep Staff Recommendation/ Board Report — May
Board Public Hearing/ Certification — June 11, 2009

Overall schedule
Issue RFQ for architect selection      April 2009 — June 2009
Site selection – Board meeting      June 2009
Public outreach/land acquisition      June 2009 — September 2009
Land acquisition process      June 2009 — August 2010
Public input/Design      July 2009 — December 2009
Design process/DSA      July 2009 — December 2010
Off-site land acquisition and Supplemental EIR (if needed)      July 2009 — December 2011
Bid and Award Phase      January 2011 — March 2011
Construction Phase March      2011 — March 2013
Off-site Construction Phase      December 2011 — December 2012
Construction Complete      March 2013
Commissioning Phase      April 2013 — July 2013
New School Opening      September 2013


                                                E-mail the Editor


Page 1   This week's print edition   Sun Dial briefs
Advertising in The Alpine Sun Staff
If your business isn't showing up in the search engines, you need to call us!